IPAC'23 - Particle Accelerator Projects and Upgrades

IPAC’23 / PARTICLE ACCELERATOR PROJECTS AND UPGRADES 35 Project Region EMEA Project Location Switzerland Project Type Project Update Project Description Upgrade of Swiss Light Source SLS to MBA Lattice Requirements List Available No Approval Date 01/01/2021 Status of Contracting 85% of storage ring items and 25% of photon beamline items are contracted Construction scheduled to start 30/09/2023 Estimated Project Cost 129MCHF Estimated Construction Duration 1.25 Type of Equipment to be Purchased all components required for a electron storage ring operating as a synchrotron radiation source Project Leader(s) Hans Braun, Alun Ashton, Romain Ganter, Markus Jörg, Phil Willmott Affiliation PSI e-mail Hans.Braun@psi.ch Contact Person(s) Hans Braun Affiliation PSI e-mail Hans.Braun@psi.ch SLS 2.0